Requirements for issuance of completion certificate and process to apply
 

Application can be made on Form B1, B2 duly signed by the allottee/attorney, approved architect and structural engineer after validation from Architecture Directorate, CDA at the Front Office, One Window Operation, CDA along with the following documents.

  • Photocopy of Form B1, B2  along with 4 copies of completion plan as per actual construction at site.
  • Estate Management dues clearance.
  • Copy of N.I.C of Allottee or Transferee or Attorney as the case may be.
  • Dues clearance from Revenue Directorate, CDA
  • Completion Scrutiny Fee as per rates of approval of building plans.
  • Proof of payment of Withholding Tax for non residential plots.
 

For further information, contact:
Forces Estates
Office# 8, 1st Floor, Irfan Mansion, Block 1-X
F-10 Markaz, Islamabad - 44000 - PAKISTAN

Voice:+92 (51) 229 3081
Voice:+92 (51) 229 3082
Voice:+92 (51) 229 9445
Cell  :+92 (300) 8503081
Cell  :+92 (301) 8503081